Winter 2025 - Progress Update
Aerial View of Progress at Oberlin Heights | Luxury Townhomes for Sale in Raleigh, NC
We’re bringing you plenty of great updates from Oberlin Heights, starting with the most significant news: PAINTED brick is complete on our first building & PROGRESS IS KICKING OFF ON BUILDING TWO.
Scroll for a full update + new site photos.
LET’S DIVE INTO THE FULL DETAILS
BUILDING ONE
Construction on Building 1 is in its final stages, with several key finishing touches coming together. Trim work is wrapping up, adding polished details to the interiors. Tile installation is nearly complete, bringing a refined aesthetic to kitchens and bathrooms. The elevators are also in the final stages of installation, ensuring smooth vertical access throughout the building.
Inside, shower glass, mirrors, and bath fixtures are being installed, signaling the near-completion of all bathrooms. Additionally, interior painting has been fully completed, giving each unit a fresh, finished look.
With all these milestones on track, we anticipate construction wrapping up by mid-March. The first move-ins are projected to begin as early as April 2025.
BUILDING TWO
Progress on Building 2 is moving forward, with foundational work nearing a key milestone. The slab has been prepped and successfully inspected, ensuring a solid foundation for the structure. The next step is pouring the concrete, which is pending favorable weather conditions, as both rain and cold temperatures can impact the timeline.
Looking ahead, Building 2 remains on schedule for an early 2026 completion. Stay tuned for further updates as construction advances in the coming months.
LET'S HIT THE HIGHLIGHTS
Building One
Trim Work:
Wrapping up, adding the final polished details to the interiors.
Tile Installation:
Near completion, enhancing the bathrooms and kitchens with high-quality finishes.
Elevator Installation:
Final stages of installation, ensuring smooth vertical access throughout the building.
Bathroom Finishes:
Shower glass, mirrors, and bath fixtures are currently being installed.
Interior Paint:
Completed, bringing a fresh and finished look to all units.
Projected Completion:
Tracking for mid-March completion, with the first move-ins possible by April 1, 2025.
Building Two
Foundation Work:
The slab has been prepped and inspected, ensuring a strong foundation.
Concrete Pouring:
Ready to proceed, pending favorable weather conditions (rain and cold).
Overall Timeline:
Tracking for early 2026 completion.
EXTERIOR OF BUILDING ONE
EXTERIOR OF BUILDING TWO
DELIVERY DATE:
Thanks to the hard work and dedication of THE OBERLIN HEIGHTS CREWS, THESE TURNKEY TOWNHOMES are STILL ON schedule. OUR FIRST OBERLIN HEIGHTS HOMES SHOULD BE MOVE-IN-READY BY spring 2025.