Spring 2025 - Progress Update
Aerial View of Progress at Oberlin Heights | Luxury Townhomes for Sale in Raleigh, NC
We’re bringing you plenty of great updates from Oberlin Heights, starting with the most significant news: OUR FIRST HOMES ARE MOVE-IN-READY!
Scroll for A PREVIEW INSIDE OUR FULLY-STAGED MODEL HOME.
LET’S DIVE INTO THE FULL DETAILS
BUILDING ONE
Our first homes are move-in-ready within Building One. They are available for touring today! Click below to schedule showing at our fully-staged model space.
BUILDING TWO
We are excited to announce significant progress on Building 2, which is now fully framed! This milestone marks a major step forward in our project. The window installation is nearly complete, allowing us to move on to the next phase with confidence. Our first interior systems build-outs are making excellent headway, with HVAC and plumbing installations well underway, ensuring that all systems are being integrated smoothly.
Looking ahead, Building 2 remains on schedule for an early 2026 completion. Stay tuned for further updates as construction advances in the coming months.
LET'S HIT THE HIGHLIGHTS
Building One
Complete: First Homes are Now Move-in-Ready
Building Two
Building Framing: Complete for Building 2.
Masonry: Just beginning.
Window Installation: Nearly finished, contributing to the building's exterior development.
Trades Work:
HVAC installation in progress.
Plumbing installation in progress.
Interior Planning: Layouts for cabinets are being finalized.
Siding Installation: Scheduled to begin soon.
Overall Timeline: Tracking for early 2026 completion.
EXTERIOR OF BUILDING ONE
EXTERIOR OF BUILDING TWO